Wind farm made by 10 wind turbines with 6 MW power each
The Grosseto wind project was born in the Maremma plain, between the Tyrrhenian coast and the first hills of the hinterland. The plant involves the installation of 10 wind turbines, each with a power of 6 MW, in the territories of the municipalities of Castiglione della Pescaia, Gavorrano and Grosseto, in southern Tuscany.
When fully operational, the wind farm will produce enough clean energy to cover the annual electricity needs of about 30,000 households, representing a concrete step towards a more sustainable energy future for the area.
DESCRIPTION: wind farm made by 10 wind turbines with 6 MW power each
EXPECTED PRODUCIBILITY: 95 480 000.00 kWh/y
POTENTIALLY AVOIDABLE EMISSIONS: 25 429 ton/y of CO2
– Scouting and site analysis
– Farm traffic and site access assessment;
– Electrical design in order to get STMG from Terna
– Technical, environmental and regulatory factors or constraints analysis for wind turbines location
– Final environmental, landscape, architectural and electrical design in order to get VIA and AU authorisation